Every S/4HANA programme reaches the same moment: the go/no-go meeting, where a date fixed for months meets the reality of the evidence. In our experience, the warning signs are usually visible weeks earlier, if someone is looking for them.
1. Rehearsal results are explained, not repeated
If mock cutovers ran long or failed steps, and the response is an explanation rather than a successful re-run, the plan has not been proven.
2. Non-functional testing is still in progress
Performance, disaster recovery and integration volume testing are often scheduled last and squeezed first. If you do not yet know how the system behaves at month-end load, or whether failover works, you are carrying unquantified risk into production.
3. Defects are being re-categorised rather than resolved
A falling count of high-severity defects is only good news if the defects were fixed. Watch for priority changes, deferrals and workarounds that depend on people remembering to apply them.
4. Security and access are unfinished
Role design, privileged access and segregation-of-duties conflicts are frequently left until the end. Going live with excessive access creates exactly the conditions attackers and fraudsters look for.
5. Nobody independent has looked
Programme teams are, understandably, invested in the date. An independent view of the evidence gives sponsors the confidence to proceed, or the justification to pause, before the cost of being wrong becomes visible to customers.
Published November 2026 by Experience Exchange. Want to discuss how this applies to your organisation? Talk to us.